Client
ArcelorMittal Europe
Location
Ghent, Belgium
Project Scope
Turnkey Smelter Relining
Completion
September 2025
PROJECT SPECIFICATIONS
Executing a Sub-Zero Tolerance Blast Furnace Refractory Upgrade
The Ghent facility is one of Europe's highest-volume continuous steelmakers. The project mandate called for a complete mechanical demolition, shell structural stiffening, and robotic gunite refractory spray relining of a 14-meter hearth diameter blast furnace under a strict 45-day plant outage timeline.
The Engineering Challenge
Temperatures within the operating hearth exceed 1,600°C. Structural steel plate deformation had to be counteracted by hydraulic jack synchronization down to 1.5mm tolerance across a 400-ton furnace ring section.
- Critical 45-day fixed commissioning deadline with severe penalty clauses.
- Robotic plasma cut-out of 80mm high-carbon boiler armor plating.
- Zero lost-time safety protocol across 240 specialist workers on site.
Project Highlights
Total Steel Plate:
1,850 Metric Tons
Refractory Mass:
3,200 Tons Gunite
Man-Hours:
148,000 Hours
Contract Value:
$38,500,000
Outcome & Operational Metrics
42 Days
Finished 3 Days Ahead of Schedule
$14.2M
Annual Energy Savings
Zero
Lost-Time Incidents