PROJECT OVERVIEW

Case Study: National Steel Smelting Plant

National Steel Smelting Plant
Client

ArcelorMittal Europe

Location

Ghent, Belgium

Project Scope

Turnkey Smelter Relining

Completion

September 2025

PROJECT SPECIFICATIONS

Executing a Sub-Zero Tolerance Blast Furnace Refractory Upgrade

The Ghent facility is one of Europe's highest-volume continuous steelmakers. The project mandate called for a complete mechanical demolition, shell structural stiffening, and robotic gunite refractory spray relining of a 14-meter hearth diameter blast furnace under a strict 45-day plant outage timeline.

The Engineering Challenge

Temperatures within the operating hearth exceed 1,600°C. Structural steel plate deformation had to be counteracted by hydraulic jack synchronization down to 1.5mm tolerance across a 400-ton furnace ring section.

  • Critical 45-day fixed commissioning deadline with severe penalty clauses.
  • Robotic plasma cut-out of 80mm high-carbon boiler armor plating.
  • Zero lost-time safety protocol across 240 specialist workers on site.

Project Highlights

Total Steel Plate: 1,850 Metric Tons
Refractory Mass: 3,200 Tons Gunite
Man-Hours: 148,000 Hours
Contract Value: $38,500,000
Consult on Similar Project

Outcome & Operational Metrics

42 Days

Finished 3 Days Ahead of Schedule

$14.2M

Annual Energy Savings

Zero

Lost-Time Incidents